The Oil and Gas Engineering Guide

blog

fr en
Publié le Mercredi 03/06/2015

Calculate the wall thickness of a pipe according to ASME B31.3

Quick design of a pressure vessel (wall thickness) according to ASME VIII div 1

Quick design of a Shell & Tube heat exchanger (required surface, shell diameter, nos tubes)

To estimate the surface of an air-cooler

To estimate a cooling tower

To understand what happens in a column tray

To understand the different types of pump seals

Sour service calculator

 



Commentaires(0)


Publié le Samedi 16/05/2015

The 2 drivers of a Project duration

One comes across a large quantity of information on a Project. It is hard to stay focus on the 2 drivers of the Project duration: Equipment and Piping, i.e.

 

1) The Critical Path of the Project is Piping.

2) Piping construction starts once Engineering is almost completed.

3) Engineering starts once Equipment purchase orders have been placed.

 

You will find more details in Chapter 16 of The Guide 2nd edition but above is the essence once must bear in mind at all times.

 

So one must focus on:

  • Placing purchase orders for Equipment in the very first months of the Project.

  • The Piping chain, particularly, the timely purchase of all types of materials and long lead ones.



Commentaires(0)